Kitchen Project

Project Lead: Arnendu     
Item # Target Date Milestone Status 
01 07/2021 Request for proposals (RFP) to prospective bidders for design Completed
02 08/2021 Receive & discuss design bids Completed
03 09/2021 Understand flood plain issues & new county regulations  Completed
04 10/2021 Design bid review and selection (click here for summary) Completed
05 11/2021 Completed
06 01/2022 Partial demolition plan & new floor plan (click here for drawings) Completed
07 02/2022 Preliminary cost estimate for construction Completed
08 03/2022 Detailed engineering design Completed
09 03/2022 Request for Proposals (RFP) to bidders for construction Completed
10 04/2022 HDBS Kitchen Project Bidder Selection Completed
11 05/2022 EB, CT, & GB approvals Completed
12 06/2022 Partial Demolition Completed
13 09/2022 Construction – Phase 1  Completed
14 12/2022 Construction – Phase 2 Completed